Projects - Sierra Grand
 

Scaffold requested had to provide a dual function:-

 

• Support System for Formwork

• Access System for finishing trades

 

False work scaffold (form support)

 

Uni-span supplied scaffold false work for the support of falsework to the underside of level 5 which was used as edge protection on the internal floors working to underside of level 5.

 

Support scaffold totalled approx 120 tons and was erected over a period of 14 working days. Upon completion of the falsework support, the scaffold was modified to provide an economical and functional access scaffold for finishing trades.

 

Perimeter scaffold

 

Roof level scaffold – A unique problem.

 

Cantilever scaffold was required off level 32 for the safe removal of 2 concrete columns.

 

Specialised cantilevered scaffold techniques were employed to minimize the risk of fall from heights and catch of falling debris, which then allowed the concrete cutter safe access to the work zone area.

 

Uni-span completed this task safely and to the complete satisfaction of the client.

 

Note: For more information or if you have a project and would like some advice from our experienced team please contact info@uni-span.com.au or call us on 07 3442 4000.

 